The California Department of Transportation announces that Pacific Gas and Electric Co. is continuing projects for the undergrounding of its infrastructure along routes in District 2. Motorists are advised to plan for delays.

Areas of PG&E undergrounding work on State Route 70 include:

  • Bucks Creek 1101: east of the Butte/Plumas County Line to west of Storrie, continued operations at various locations through this fall with delays of up to 15 minutes Monday through Friday between 7 a.m. and 5:30 p.m.
  • Bucks Creek 1102: west of Storrie to east of Caribou Road, continued operations at various locations through this fall with delays of up to 15 minutes Monday through Friday between 7 a.m. and 5:30 p.m.
  • Gansner: between the Greenville Wye junction with SR 89/70 and Keddie, roadway restorations currently anticipated for late July, with delays of up to 15 minutes possible during daytime hours

SR 89 projects include:

  • Crescent Mills permit work: between Greenville and the Greenville Grade, currently in construction through early fall with no mainline lane closures currently anticipated with the work
  • Greenville permit work: south of Greenville Dump Road to east of Standardt Mine Road, construction underway with majority of work on shoulders and no traffic impacts; traffic control at times as needed, with delays of up to 15 minutes Monday through Friday during daytime hours